SECTION EIGHT: FINANCIAL OVERVIEW

JMIG Port & Logistics Infrastructure - Forécariah, Guinea

First Phase Development - Climate-Resilient Deepwater Port

1. PROJECT CAPEX SUMMARY

Total First Phase Investment: €210 Million - Fully Costed

Component Description Estimated Cost % of CAPEX
A. Access Infrastructure 5km Climate-Resilient Access Road (Almamyah - Port Platform), drainage, lighting, weighbridge €45M 21.4%
B. Marine Structure 2km Offshore Bridge (piled) + 450m x 50m Port Platform, berthing dolphins, fenders €95M 45.2%
C. Port Equipment Mobile harbour cranes, forklifts, 5,000m2 cold chain, 10,000m2 warehousing, fisheries processing, power & water €28M 13.3%
D. Environmental & Social Full ESIA, IFC Performance Standards 1-8, Resettlement Action Plan, Biodiversity Offset, Maritime Safety €12M 5.7%
E. Contingency & Management 15% Physical & Price Contingency, PMC (Egis/BRL), Legal (OHADA/EU), Insurance, Lender's Advisor €30M 14.3%
TOTAL First Phase - Ready for DFI Closing €210M 100%

2. FUNDING STRUCTURE - EU GLOBAL GATEWAY BANKABLE

Source Amount % Status Instrument
Consortium Equity (Host) €31.5M 15% Committed - Proof of Funds Common Equity
DFI Senior Debt - EIB / Proparco €126M 60% Under Appraisal - EU Global Gateway Infrastructure Envelope 18yr Senior Debt @ 6.5%
Climate & Blue Economy Grant €21M 10% EU-Africa Infrastructure Fund + Blue Economy Window Non-repayable Grant
Commercial Debt / Off-taker Pre-finance €31.5M 15% Advanced Discussion with Bauxite Off-takers 7yr Pre-export Finance
TOTAL €210M 100% Financial Close Target: Q2 2027

Consortium shareholding structure as defined in Section Nine: Board & Chair Representatives. Individual equity contributions are subject to private Shareholders Agreement and not disclosed publicly.

3. REVENUE MODEL (25-Year Concession + 10 Year Extension Option)

A. ANCHOR REVENUE - BAUXITE (Bankable Off-taker)

B. DIVERSIFIED REVENUE (Climate-Resilient)

Revenue Stream Driver Year 1 Year 3 Full Ramp
1. Container & General Cargo 120,000 TEU + Bulk minerals €22M €32M
2. Logistics Corridor Toll 800 trucks/day @ €50 avg €14.6M €18.2M
3. Cold Chain & Warehousing Lease 5,000m2 @ EU-certified -80% utilization €15M €22M
4. Fisheries Export Fees 50,000 tons certified export @ €120/ton €6M €12M
5. Marine Services Tug, Piloting, Bunkering, Fresh Water €12M €19.8M
SUB-TOTAL DIVERSIFIED €69.6M €104M

TOTAL PROJECTED REVENUE:

Concession Period: 25 years + 10 year extension at Government of Guinea option

4. FINANCIAL INDICATORS - WITH BAUXITE ANCHOR

5. OPEX & SUSTAINABILITY

6. USE OF FUNDS - NEXT 18 MONTHS (Phase 1a: €15M)

Phase Timeline Amount Deliverable
1a-i Q4 2026 - Q1 2027 €5M Detailed Design, Bathymetric & Geotechnical Survey, Marine EIA
1a-ii Q1-Q2 2027 €6M Full ESIA, IFC PS Compliance, Resettlement Action Plan, PPP Concession Signature
1a-iii Q2-Q3 2027 €4M Lender's Technical Advisor, Financial Close, EIB/Proparco Credit Approval
TOTAL Phase 1a €15M Ready to Construction

7. SENSITIVITY ANALYSIS

Scenario Revenue NPV @10% IRR Project
Base Case - 5 MTPA Bauxite €115M Y1 €312M 28.4%
Downside - 3 MTPA Only €89M Y1 €178M 21.2%
Upside - 8 MTPA Bauxite €145M Y1 €428M 33.1%
Without Bauxite €38M Y1 €42M 13.1%

Bankability Note: Even in downside (3 MTPA), DSCR stays >1.5x - Project remains bankable without bauxite.